Regarding: City Hall Parking Lot Project
CC: Debbie Sutherland, Scott Thomas, Bob Greytek

I am going to vote against the City Hall Parking Lot project. Here are three reasons you should, too:
First, On March 24, 2014 during the Committee Session immediately preceding Special Meeting of Council in which Council passed Resolution 14-35 authorizing the City to apply for the Ohio EPA’s Surface Water Improvement Fund (SWIF) grant, the City’s Service Director, Scott Thomas, told Council “there are no matching funds” required by the grant.(1)

Subsequently, on August 3, 2015, Mr. Thomas informed Council that the City would have to spend $64,408, in addition to $120,000 SWIF grant, to complete this project.(2) Although the grant does not require matching funds, the Administration should have made it unambiguously clear on March 24, 2014 that the project would require additional funds from the City. I consider that a material omission.

Also on March 24, 2014, Mr. Thomas told Council there would be “no loss of existing parking spaces” as a result of this project.(3) On August 3, 2015, Mr. Thomas informed Council that 7 parking spaces – over 10% of the existing parking spaces – will be eliminated.(4) Although I believe Mr. Thomas’s statement on March 24, 2014 was most likely made in good faith, it was, nonetheless, inaccurate. I am also uncertain at this moment whether the parking lot to the west of City Hall is – or should be – included in this project.

In my opinion, Council received a combination of ambiguous/incomplete and inaccurate information immediately prior to our vote on March 24, 2014. Therefore, I feel no obligation to vote in favor of this project even though I voted in favor of the grant application. The terms of the deal have changed.

Second, On August 3, 2015, Mr. Thomas told Council that just one company, Licursi Construction, Inc. (LCI), bid on the City Hall Parking Lot project. When asked why, the City’s Consulting Engineer, Bob Greytek, explained that “it is hard to find contractors to bid [at] this time of the year.”(5)

In my opinion, the City should have sought bids at a time of year when it is not hard to find contractors to bid on projects. Such action may have led to the receipt of multiple bids. As the Mayor recently said, in reference to an unrelated project regarding audio equipment, when the City is spending taxpayer dollars it is obliged to undertake projects “as cost effectively and efficiently as possible. We can’t do that without a second quote, and maybe a third quote.”(6)  I agree with the Mayor on that point.

It should be noted that LCI is the same company that installed the tennis courts near City Hall. Those courts do not drain properly. The City has had in its possession, since October 2013, a memo which, in my opinion, if accurate, appears to indicate that LCI informed the City at an appropriate time that the tennis courts would not drain properly. Rather than address the issue, the City instructed LCI to proceed with the project as planned because “they did not have the funds.”(7) The Administration never asked Council to vote on appropriation of additional funds to correct the error. That should have been done. Council routinely authorizes additional funds when the actual cost of a project exceeds its budget.

Further, the Administration did not disclose this memo to Council until after our vote on August 3, 2015 regarding whether or not to authorize LCI to install the parking lot. In my opinion, the Administration’s decision to withhold this information from Council until August 5, 2015 was inappropriate, particularly given that it was requested during a July 29, 2015 Finance Committee meeting. (8)

I am no longer primarily concerned about LCI. I am concerned about authorizing a large, taxpayer-funded project – particularly one involving Ohio EPA funds – after receiving just one bid. The Mayor recently reminded all of us, and the public, that the City needs two or three quotes for large, taxpayer-funded projects. I cannot, in good faith, explain to my constituents why this project is “special” and I cannot defend the City’s choice to seek bids at a time of year when it’s hard to find contractors to bid.

Third, perhaps most importantly, it is important to look at the big picture. After the Council meeting on August 3, 2015, the Mayor informed Council, via email, that “[t]he parking lot is in bad condition and Council will have to appropriate $120k + to do a basic improvement” (9) if we do not authorize this project.

Although I understand that from the City’s perspective it may seem less expensive to spend $64,408 of our residents’ tax dollars on this project [or possibly more if there are problems under the parking lot similar to the problems under the tennis courts] by combining those funds with another $120,000 from the Ohio EPA, it’s important to remember that our constituents have provided all $184,407 of those dollars. The people of Bay Village pay taxes to both City of Bay Village and the State of Ohio.

In my opinion, spending 50% more total tax dollars to install this new parking lot surface instead of completing a “basic improvement” is not a responsible use of our constituents’ money. I do not believe that the incremental benefits outweigh the incremental cost. Further, while I strongly encourage the City to seek grants that reduce the expenditure of our residents’ tax dollars for worthwhile projects, I do not believe that we should spend more total taxpayer dollars simply because the State has offered them.

In Closing, I oppose this project. I ask that you vote “NO” with me. We received ambiguous/incomplete and inaccurate information prior to our vote to authorize the application for this grant. The City received just one bid for the project. The Administration withheld information from Council about a prior project involving this contractor, and this parking lot surface costs 50% more than a basic improvement.

The next time I’m in front of my constituents, I will tell them I voted against this project because I believe we should dedicate this money to the streets and sewers in front of their houses – not to an expensive new parking lot surface where city employees park for work.

(1) March 24, 2014 Committee Meeting of Council Minutes, page 4
(2) August 3, 2015 Committee Meeting of Council Minutes (unapproved draft as of 8/10/15), page 2
(3) March 24, 2014 Committee Meeting of Council Minutes, page 4
(4) August 3, 2015 Committee Meeting of Council Minutes (unapproved draft as of 8/10/15), page 4
(5) August 3, 2015 Committee Meeting of Council Minutes (unapproved draft as of 8/10/15), page 2
(6) June 22, 2015 Special Meeting of Council Minutes, page 4
(7) October 29, 2013 Memo TO: Daniel Galli FROM: Licursi Construction, Inc. RE: Cahoon Park, “10/01/12”
(8) July 29, 2015 Finance Committee Meeting Minutes, page 9
(9) August 3, 2015 E-mail TO: City Council FROM: Debbie Sutherland RE: Council Meeting